top of page
Writer's pictureRachel Hounsell-Roberts

What is a schedule of works in construction?

Updated: Nov 4


Our guide to construction schedules of work. [Includes a free downloadable template]



Click here to get a quote


A schedule of works (SOW) is an instructional list of works requested/intended, that is often produced for smaller projects. It allows for pricing, so is similar to a bill of quantities (BOQ) but it doesn’t include quantities. It’s the contractor's responsibility to input the measurements and quantities that ensure correct pricing.


Schedules of work are likely to be produced alongside drawings, specifications, etc. to form part of a tender pack. It’s important for schedules of work to correctly describe all significant items of work which they relate to. If there are inaccuracies, it can create friction with the contractor in the construction phase.

 

Why is a schedule of works important?


  • Provides clarity on the project requirements

  • Allows the contractor to price more accurately

  • Limits conflict or disagreements with the contractor linked to the scope of works

  • The contractor holds the responsibility for inputting quantities

 

In a schedule of works you should create different sections for the proposed works. The following items are normally included (the examples used below would require greater detail in practice):


1.       Main summary

The main summary provides an overview of all sections totals and the overall project sum. 


Screenshot of  a spreadsheet showing the main summary section of a schedule of works

2.     Preliminaries

 

These are items that are essential for the contractor to complete the work, such as site accommodation, temporary services, etc, but not the materials and labour directly required for the works.


Screenshot of the Preliminaries section of a schedule of works

 

3.     Facilitating works


This is the work required to prepare the site for refurbishment (also referred to as ‘strip out’). If an element is to be kept, this may be listed in the facilitating works, stating that the item will ‘remain’.



Screenshot of the Facilitating Works section of a schedule of works

4.     Internal refurbishment

 

This includes all the desired internal refurbishment works. It’s important to include as much detail as possible here. Additional clarifications can be requested from the contractor on what has been allowed for in the pricing.


Screenshot of the Internal Refurbishment section of a schedule of works

 

5.     External works/refurbishment


This includes all works to the external of the property.


Screenshot of the External Works section of a schedule of works

 

Once a contactor has priced the schedule of works it’s important that all rates are checked (and if they seem high, check these against SPONS), and that the quantities the contractor has inputted are accurate.

The agreed price can be used as the contract price and the schedule of work listed as associated documentation.


Download our free schedule of works template here:



Overall, a schedule of works provides a detailed list of works required for tendering contractors to quantify and price a project. There are often associated drawings and schedules which go alongside the SOW. If done correctly, this improves clarity around the project scope and minimises disputes.


Call to action button: click here to ask us to deliver your construction project

Author


A photo of the author

Rachel Hounsell-Roberts

Rachel is currently working towards a BSc (Hons) in Construction Management. She has taken the lead on managing the fitout of quick-service restaurants for an international franchise, developing a franchisee fitout design and process guide for a new franchise.


19 views0 comments

Recent Posts

See All

Comentarios


bottom of page